20211201 Bungalow construction (workshop steps) - day 148

Fabrication of the steps to access to workshop Sanggah temple intersecting steps bring tight interaction between the two structures.

igb

26.94
Hive.Blog

20211128 Bungalow construction (ceiling fixtures) - day 145

Ceiling fans and spotlights Main space Bedroom Bedroom electrical panel

igb

26.94
Hive.Blog

20211030 Bungalow construction (workshop wall smooth render) - day 116

Workshop entrance Electrical switches Witnessing water well being drilled through workshop entrance Mixture of cement and plaster for ...

igb

26.94
Hive.Blog

20211029 Bungalow construction (main space wall frames) - day 115

The only brick wall in the main space with entrance door and electrical panel. The kitchen wall with single wall-long shutter. Met...

igb

26.94
Hive.Blog

20211028 Bungalow construction (bedroom walls plastering) - day 114

igb

26.94
Hive.Blog

20211024 Bungalow construction (bedroom wall color) - day 110

The bedroom walls with be colored dans la masse. To that end we add pigments to the cement used for the last coat and we will probably ke...

igb

26.94
Hive.Blog

20211023 Bungalow construction (bedroom wall construction) - day 109

Arie and his team install door frames Windows flanking columns Behind this wall is the bathroom Inside bathroom General view wit...

igb

26.94
Hive.Blog

20211021 Bungalow construction (roof gutter) - day 107

PVC gutter Custom metal brackets for gutter Installing gutter on bedroom roof Gutter installed.

igb

26.94
Hive.Blog

20211018 Bungalow construction (Sanggah temple construction) - day 104

Completion of the first level of the Sanggah temple

igb

26.94
Hive.Blog

20211013 Bungalow construction (wall mounted toilet) - day 99

Wed. Oct. 13, 2021 Geberit wall-mounted toilet is installed in the workshop. First the wall unit... then the toilet seat... mounts ont...

igb

26.94
Hive.Blog

20211010 Bungalow construction (septic system) - day 96

Concrete tops are poured to close the septic chambers that were installed two days ago Main system Workshop system The cylinder is ...

igb

26.94
Hive.Blog

20211008 Bungalow construction (septic system) - day 94

Chambers for the septic tanks and absorbers are coming together. The septic tank treats the material then transfers the resulting liquid ...

igb

26.94
Hive.Blog

20211003 Bungalow construction (roof installed) - day 89

Roof of first structure is complete. We're assessing possible solutions for roof corners. We use Trimdek as roofing material. ...

igb

26.94
Hive.Blog

20210929 Bungalow construction (septic excavation) - day 85

Excavating the earth for the septic tank of the workshop. The two septic tanks.

igb

26.94
Hive.Blog

20210920 Bungalow construction (roof mesh) - day 76

We changed the roof mesh that we started using the other day. This new 5cm x 5cm x 3mm mesh is much better. It doesn't buckle nearly as...

igb

26.94
Hive.Blog

20210918 Bungalow construction (gutter concrete) - day 74

In parallel with the installation of the metal structures the gutter in front of the property is being created. It's intense work that ...

igb

26.94
Hive.Blog

20210912 Bungalow construction (painted rafters) - day 68

The rafters of the first structure are installed ... ... and get a new coat of root color paint selected a couple of days ago Trimde...

igb

26.94
Hive.Blog

20210908 Bungalow construction (metal paint color selection) - day 64

Color selections. Tests And the winner is: Indaco 80269R (2895) Root The one on top in the last image.

igb

26.94
Hive.Blog

20210904 Bungalow construction (slab rebar) - day 60

We are a couple of days from the main concrete pour of the project, the floor onto which both metal structures will stand. Most rebars ...

igb

26.94
Hive.Blog

20210831 Bungalow construction (beams formwork) - day 56

Formwork for the beams that will support the concrete slab above the workshop. In the center of this photo you can see the bathroom wal...

igb

26.94
Hive.Blog

20210828 Bungalow construction (swing wall) - day 53

Meanwhile at the warehouse, the first swing wall is almost done. Point of rotation with heavy duty ball bearings Huda and Yadi, welde...

igb

26.94
Hive.Blog

20210826 Bungalow construction (removing formwork) - day 51

igb

26.94
Hive.Blog

20210824 Bungalow construction (workshop formwork) - day 49

Finishing the formwork and getting ready for the big day (tomorrow) during which we will pour the floor and the walls of the workshop in ...

igb

26.94
Hive.Blog

20210822 Bungalow construction (metal structure delivered) - day 47

Finished rafters for both roofs are now on site. https://youtu.be/Zb61khwXIUY Columns. Supports for the cantilevered part of the roof...

igb

26.94
Hive.Blog

20210808 Bungalow construction (retention wall) - day 33

Arnaud visiting the site today. The brick part of the workshop retention wall is complete. Water lines for the bathroom are laid in the...

igb

26.94
Hive.Blog

20210806 Bungalow construction (lean concrete) - day 31

Lean concrete is complete. https://flyvision.org/superstition_bungalow/assets/20210806SuperstitionBungalow.1.jpg Metal being installed i...