20211207 Bungalow construction (door lock reference) - day 154

References and ideas for the door lock mechanism that Arie and his crew are working on

igb

26.94
Hive.Blog

20211203 Bungalow construction (bedroom shutters) - day 150

Each of the 8 bedroom windows gets a wooden shutter. Shutters are installed inside. Custom metal hinges made by Arie and crew connect ...

igb

26.94
Hive.Blog

20211201 Bungalow construction (workshop steps) - day 148

Fabrication of the steps to access to workshop Sanggah temple intersecting steps bring tight interaction between the two structures.

igb

26.94
Hive.Blog

20211129 Bungalow construction (water well digging complete) - day 146

The boring of the well which started 40 days ago is finally complete. Water tested at a depth of 60 meters was plentiful and high qualit...

igb

26.94
Hive.Blog

20211128 Bungalow construction (ceiling fixtures) - day 145

Ceiling fans and spotlights Main space Bedroom Bedroom electrical panel

igb

26.94
Hive.Blog

20211126 Bungalow construction (Trimdek walls) - day 143

Inside the main space East swing wall. This entire wall swings open to offer an unobstructed view of the rice fields. West swing wall. ...

igb

26.94
Hive.Blog

20211124 Bungalow construction (Sanggah temple complete) - day 141

The Sanggah temple is complete. It is made of concrete, bricks and plastered with cement mixed with black sand from the nearby beach foll...

igb

26.94
Hive.Blog

20211123 Bungalow construction (outdoor light fixtures) - day 140

Installation and test of 20 exterior light fixtures on two bungalows.

igb

26.94
Hive.Blog

20211121 Bungalow construction (cement tiles) - day 138

The cement tiles that we designed and produced a couple of months ago are now being installed on the toilet walls of both bathrooms.

igb

26.94
Hive.Blog

20211119 Bungalow construction (window glass install) - day 136

Glass is being installed today on 8 bedroom windows.

igb

26.94
Hive.Blog

20211116 Bungalow construction (Sanggah temple progress) - day 133

Prepping for the fabrication of the top part of the temple Working on the last structural element. Temple is complete. Last step is ...

igb

26.94
Hive.Blog

20211113 Bungalow construction (kitchen pantry) - day 130

Pantry side walls are made of reinforced concrete The back wall is cement plastered. Direct connection from cement plaster to metal...

igb

26.94
Hive.Blog

20211111 Bungalow construction (Trimdeck walls) - day 128

Installation of the Trimdek on the metal frames of the walls of the main space has started. It I the same marterial that we used on t...

igb

26.94
Hive.Blog

20211110 Bungalow construction (rounded corners) - day 127

All cement and concrete walls have 2cm radius rounded corners. Bedroom. Unfinished wall. Workshop. Finished wall.

igb

26.94
Hive.Blog

20211109 Bungalow construction (door lock) - day 126

Today Arie is showing us progress on the there-point locking system that he's been working on for entrance doors. Designing and buildin...

igb

26.94
Hive.Blog

20211108 Bungalow construction (electrical fixtures placement) - day 125

We're almost at the stage where we can install electrical fixtures. Since many fixtures are installed following pentagonal symmetry, we'...

igb

26.94
Hive.Blog

20211107 Bungalow construction (new well drill) - day 124

We had been warned by the locals that it would be challenging to drill a water well. The underground in the is area of Bali is composed o...

igb

26.94
Hive.Blog

20211106 Bungalow construction (bedroom wall textured finish) - day 123

The first wall finish sample is not conclusive. They did a lazure with vertical strikes which is not what we are looking for. In order...

igb

26.94
Hive.Blog

20211105 Bungalow construction (outdoor light fixture) - day 122

We're trying to hire local artisans as often as possible. It is not uncommon to have discrepancies between the original design and the re...

igb

26.94
Hive.Blog

20211104 Bungalow construction (bedroom shutters) - day 121

The wood for the bedroom shutters is going stay natural. We keep the stains and the marks of time. After gentle sanding, planks will be ...

igb

26.94
Hive.Blog

20211102 Bungalow construction (bedroom electrical conduits) - day 119

Positioning fixtures, switches and outlets with bed axis as reference. Prepping wall to receive conduit for main electrical panel ou...

igb

26.94
Hive.Blog

20211030 Bungalow construction (workshop wall smooth render) - day 116

Workshop entrance Electrical switches Witnessing water well being drilled through workshop entrance Mixture of cement and plaster for ...

igb

26.94
Hive.Blog

20211029 Bungalow construction (main space wall frames) - day 115

The only brick wall in the main space with entrance door and electrical panel. The kitchen wall with single wall-long shutter. Met...

igb

26.94
Hive.Blog

20211028 Bungalow construction (bedroom walls plastering) - day 114

igb

26.94
Hive.Blog

20211027 Bungalow construction (silver plated hardware) - day 113

We're planning to use silver plating as an anti-rust solution for the custom metal hardware that we are designing. Our silversmiths in Ce...

igb

26.94
Hive.Blog

20211026 Bungalow construction (gutter puzzle) - day 112

PVC rain gutters are installed all around the roof of each structure. Water is collected from the gutters at each corner, so 5 times per ...

igb

26.94
Hive.Blog

20211025 Bungalow construction (outdoor wall light) - day 111

There's an opportunity for a recessed outdoor light fixture on both sides of each column. Here's a drawing of our second (and final) vers...

igb

26.94
Hive.Blog

20211024 Bungalow construction (bedroom wall color) - day 110

The bedroom walls with be colored dans la masse. To that end we add pigments to the cement used for the last coat and we will probably ke...

igb

26.94
Hive.Blog

20211023 Bungalow construction (bedroom wall construction) - day 109

Arie and his team install door frames Windows flanking columns Behind this wall is the bathroom Inside bathroom General view wit...

igb

26.94
Hive.Blog

20211021 Bungalow construction (roof gutter) - day 107

PVC gutter Custom metal brackets for gutter Installing gutter on bedroom roof Gutter installed.